Simhapuri Energy to synchronize its 300 MW Phase I near Nellore

Madhucon Infra Limited, a subsidiary of Madhucon Projects Limited is setting up a 1,920 MW coal based power project near Nellore ( Thamminapatnam village, SPSR Nellore District near Krishnapatnam Port) through a special purpose vehicle Simhapuri Energy Pvt Ltd. Phase-I construction of of 300 MW is complete in all respects. Boiler light up process has commenced and the company is now heading towards synchronization of Phase – I.

Another 300 MW Phase – II is planned to be commissioned by August, 2012. Simhapuri Energy has also applied for clearances for its 1320 MW Phase – III and hope to start the commissioning activities by 3rd or 4th quarter of 2012.